Construction technology of hard polyvinyl chloride UPVC pipe
欄目:Industry News 發布時間:2021-06-03 15:19
In water well engineering, the traditional pipes used to build wells are mainly cast iron pipes, steel pipes and concrete pipes. These pipes have serious corrosion and aging problems, which have been difficult to solve. Compared with traditi...
In water well engineering, the traditional pipes used to build wells are mainly cast iron pipes, steel pipes and concrete pipes. These pipes have serious corrosion and aging problems, which have been difficult to solve. Compared with traditional well pipes, polyvinyl chloride PVC-U pipes have uniform performance, strong corrosion resistance, light weight, abrasion resistance and biological inertness, low water flow resistance, long service life, simple and rapid installation, and low cost And other distinctive features.

1 Well completion process
1.1 Preparation for well completion
(1) Correct the hole depth. After the drilling is completed, the hole depth is corrected, and the steel ruler is used to accurately measure all the drilling tools raised from the hole. The hole depth error shall not be greater than 2.
(2) Test hole. After the hole is drilled, test the hole in time to check whether the diameter of the hole meets the requirements, whether the hole is vertical and round, to ensure the smooth installation of the well pipe and the uniform thickness of the gravel. It is advisable to use a steel hole tester to test holes. The length of the hole tester is 20-30 times the diameter of the hole, and the diameter is 20mm-30mm smaller than the diameter of the hole.
Impact drilling test hole: The hole tester is connected to the end of the drill wire rope, and the hole tester can smoothly go to the bottom of the manhole. Drilling: fL I~P qualified.
Rotary drilling test hole: The hole tester is connected with the drill rod to drill the hole. While running the drilling tool, rotate the drill rod manually, and if it goes down to the bottom of the hole smoothly without any resistance, the drilling meets the requirements. Otherwise, put forward the drill bit to repair the hole until the drilling meets the requirements.
(3) Piping. According to the stratum profile divided by drilling and hydrological logging, the location of the filter pipe and the filling location of different specifications of filter materials are determined, and the actual structure of the well is compiled. The filter tube and filter material should be selected according to the aquifer particle screening data. If the prepared filter tube and filter material specifications do not match the screening data, the filter tube and filter material that meet the requirements should be replaced.
When piping, check the quality of the well pipe, carefully check the fit of the threads, and clean the threads; use a steel ruler to measure the length of each well pipe. And use a marker to number the upper and lower pipes on the well pipe according to the actual well structure drawing.
(4) Drill hole cleaning. Before the well pipe is installed, the hole depth and diameter should be accurately measured, and the hole should be cleaned. The percussion drilling hole is used to draw out the drill cuttings and thick mud that settled at the bottom of the hole with a suction tube. After the rotary drilling hole is tested, the drilling tool should be lowered to the bottom of the hole again, and the mud pump should be activated to flush the cuttings deposited at the bottom of the hole out of the hole, and the mud should be thinned out.
1.2 Well pipe installation
(1) The bottom of the sedimentation tube must be set up at the bottom. The bottom of the tube should be processed with a PVC-U board with a thickness of 20mm~30mm or made of other materials that can ensure the bottom of the seal. The bottom of the tube and the precipitation tube can be connected by plastic welding, epoxy resin bonding, mechanical riveting, etc., but it must be ensured The connection is firm and reliable.
(2) The method of direct lifting and one-off pipe down is adopted. When running down the pipe, the well pipe may float before the water filter pipe enters the water (due to the low pipe density, PVc-u well pipe density: 1.35 ~ 1.45g/cm.) sinking is difficult, you can take the well Water is injected into the pipe to increase its weight and help it sink.
(3) Set up a centralizer. In order to locate the well pipe in the center of the borehole and ensure the uniform thickness of the gravel packing, centralizers must be installed at the appropriate positions of the water filter pipe and the well wall pipe when installing the well pipe. The number of centralizers per well shall not be less than 3 (configured according to the actual well depth). The distance between centralizers is generally 30m~50m, and the diameter of centralizers is 50mm~60mm smaller than the borehole diameter. The centralizer can be made of wood, PVC—U board length should not be less than
600mm, thickness 30mm~50mm. 4 pieces of wood centralizers should be evenly distributed along the circumference of the pipe and tied firmly with iron wires; 3 pieces of UPVC centralizers should be evenly distributed along the circumference of the pipe, which can be bonded by adhesive or tied by iron wires.
Whether it is wire binding or adhesive bonding, it should be ensured that the supporting device is firm and reliable.
(4) The well pipe adopts press-formed thread. When lowering the tube, after twisting the thread to the end by hand, you must use hemp rope and wooden sticks or V-belt and wooden sticks to further tighten it.
(5) The lowering speed in the manhole under the well pipe should be uniform and slow. If you encounter obstacles during the down-pipe process, you should find the cause in time. Solutions such as moving up and down and turning the well pipe slightly clockwise, etc. can be taken, without piercing. If the treatment is invalid, the well pipe should be removed from the hole in time. It is strictly forbidden to knock with metal utensils during the lowering process.
(6) The well pipe must be lowered to the bottom of the hole, and pipe hanging is strictly prohibited. After the well pipe goes down to the bottom of the well, a spirit level should be used to measure the verticality of the well pipe and the levelness of the wellhead, and check the size of the exposed ground as required. When all the requirements are met, fix the well pipe mouth, and use the drilling rig hoist to apply tension to the well pipe (natural hanging state) before enclosing the filter material.
1.3 Gravel filling
(1) Filter material selection. The quality and specifications of the filter material should be carefully checked before gravel filling (the quality and specifications of the filter material shall be implemented in accordance with the relevant technical specifications), and the filter material that does not meet the requirements shall not be filled in the manhole. The filter media containing more soil impurities should be rinsed with water before being used. Measure the number of filter materials stored on site and calculate whether the number of filter materials meets the design requirements. The filter material preparation should be sufficient.
(2) Gravel filling. According to the characteristics of UPVC well pipes, the gravel filling method should adopt the flushing gravel filling method. According to the actual situation of the well site, the pumpless gravel packing method or air compressor reverse circulation flushing gravel packing method can also be adopted. The gravel should be filled continuously and evenly around the well pipe from the wellhead, and should not be filled from a single direction. The filling speed must not be too fast. During the gravel filling process, the position of the filter material surface in N:fL should be checked regularly. If blockage or "bridging" is found, measures should be taken to eliminate the gravel before filling. After the filter material is filled to the predetermined position, the surface of the filter material should be measured again before the water stop or external sealing of the pipe
If there is a sinking position, it should be filled to the predetermined position.
Wash the gravel. After running the pipe, lower the drill pipe from the inside of the pipe to a distance of lm~2m from the bottom of the well pipe, and take measures to close the pipe mouth, and start the water pump to inject water from the drill pipe into the well pipe. The amount of water injection shall be subject to not flushing out the filter material. After the annulus outside the pipe returned water, gravel filling began. During the gravel filling process, the flushing fluid should always be circulated and the pump should not be stopped midway.
No pump to fill gravel. Gravel packing H~: The liquid in fL should always keep overflowing from the well nozzle. If the overflow is interrupted, measures must be taken to refill the gravel until the well pipe mouth resumes overflow.
The air compressor washes the gravel in reverse circulation. The orifice should be connected to the water source when filling gravel. The flushing fluid should always circulate over the hole.
1.4 Waterstop and sealing
(1) Water stop material. Waterstop materials should meet the requirements of relevant regulations, and high-quality clay balls or cement slurry should be used. Generally, high-quality clay balls are preferred for permanent water stop. When a well is formed in a high-pressure artesian zone or there are special requirements for water stopping, cement slurry or colloidal cement slurry should be used for permanent water stopping.
(2) Clay balls stop water. The clay ball is made of high-quality clay, the diameter of the clay ball is 20mm~30mm. Let it cool and dry before use until the surface is slightly dry and the inside is moist and soft. When using clay balls to stop water, the clay balls should be filled continuously and evenly around the well pipe from the wellhead, and should not be filled from a single direction, and the speed of putting the clay balls should not be too fast. During the process of putting the clay ball, the position of the clay sphere in the hole should be detected regularly. If blockage is found, measures should be taken to eliminate it before throwing the clay earth. ’
(3) Cement slurry to stop water. When using cement slurry to stop water, it is advisable to use ordinary Portland cement or aluminum sulfate geological prospecting cement of 32.5Mpa or more. Concentrated quick-drying cement should not be used. In order to prevent the water chemical reaction heat generated by the cement slurry from affecting the UPVC well pipe If the strength is affected, 2-9 bentonite should be added to the cement slurry to eliminate the heat generated by water chemistry.
After the clay ball is filled to the predetermined position, the position of the clay sphere should be measured again before the clay backfilling and sealing outside the pipe. If there is sinking, it should be filled to the predetermined position and backfilled with clay. If you want to check the water stop effect, you can do it before backfilling.
1.5 Well wash
Well washing should be carried out after gravel filling and water-stopping clay is backfilled to the ground level, 24 hours after the procedures are completed. According to the characteristics of UPVC well pipes, sodium pyrophosphate or compressed air should be used for well washing. Pistons can also be used to wash wells.
(1) Sodium pyrophosphate washes wells. Sodium pyrophosphate or sodium hexametaphosphate should be cleaned according to relevant specifications. In order to achieve a good well cleaning effect, before cleaning the well, the mud used for drilling and the mud on the hole wall should be tested indoors, the medicament should be dosed according to the test results, and the well should be pumped and washed regularly.
(2) The compressed air well flushing shall be carried out in accordance with the relevant prescribed procedures. In order to reduce the pressure difference between the inside and outside of the well pipe, the air injection speed should be controlled.
(3) Piston washes well. If a piston is used to clean the well, the following requirements should be met: the diameter of the piston should be 20mm~30mm smaller than the inner diameter of the well tube (the steel platen should be 50mm~60mm smaller than the inner diameter of the well tube), and the length of the piston should be 80mm~100mm. The lifting speed of the piston should not be too fast, and should be controlled between 0.4 and 0.8 m/s. When using steel wire rope weighted drill rods to drive pistons to wash wells, elastic centralizers must be installed on the weighted drill rods to prevent damage to UPVC well pipes. The well is cleaned from top to bottom step by step, and the piston cannot stay in the hole for a long time.

2 Problems and countermeasures in construction
(1) Existing problems. When there is no seat at the bottom of the well during construction, the water level in the pipe will drop after the well is washed, and the mud and filter material outside the well pipe will sink and drive the lower well pipe to sink. The upper well pipe cannot follow the pressure of the backfill at the same time. When sinking, the well pipe is prone to be disconnected, causing waste wells.
(2) Countermeasures. First of all, try to place the well pipe at the bottom of the well. After the well pipe is down to the bottom of the well, the well pipe can be lifted by lm~2m again, and then the well pipe can be quickly dropped to the bottom of the well after aggravating, so that the well pipe can be seated at the bottom of the well several times . In addition, when the well pipe is installed, 4 holes can be drilled at the 1:1 position of the well pipe and anchored with screws, so that no disconnection occurs when the well pipe sinks. After the well is washed, the filter material and the backfill can be solidified. The well maintenance was successful.

Wuxi Jiahong Plastic Technology Co., Ltd. can process various filled, flame-retardant, reinforced modified ABS, PS, PC, PC/ABS, polypropylene, PA and other engineering plastic particles according to customer requirements; various automotive door panels, bumpers, dashboards , Engine cover, car lights and other automotive special materials.

Wuxi Jiahong Plastic Technology Co., Ltd. has nearly 30 years of experience in R&D and pelletizing production of PVC pellets, and experience in R&D and production of modified engineering plastics; the professional technical service team can provide customers with one-stop modified plastic system solutions. If you want to know more about the product, please log in to our official website: www.zpinjie.com, consult online customer service or call the hotline. Landline: 0510-68755207 Mobile: 15190220696, we will serve you wholeheartedly.
久久久久久人妻精品一区二区三区 | 狠狠躁夜夜躁AV网站色| 成 人 A V免费视频在线观看| 永久免费无码AV在线网站| 午夜亚洲乱码伦小说区69堂| 日本三级强伦姧护士HD| 欧美噜噜久久久XXX| 免费看含羞草AV片成人网站| 久久久WWW免费人成精品| 国产亚洲成AⅤ人片在线观看蜜桃| 国产成人精品一区二区三区免费| 吃了继兄给我开的药我做的梦| NARUTOMANGA全彩纲手| 撞击成熟美妇老师后臀| 伊人狠狠色丁香婷婷综合| 亚洲色成人网一二三区| 亚洲精品国产一二三无码AV| 亚洲AV无码一区二区三区人区| 无码人妻精品一区二区三区免费| 色综合久久久久无码专区| 人C交ZO〇Z〇〇XX| 欧美最猛黑人XXXXX猛交| 欧美成人影院亚洲综合图| 美丽的熟妇中文字幕| 久久一区二区三区精华液| 久久大香香蕉国产拍国| 久久精品国产亚洲AV蜜桃| 久久精品国产亚洲AV水果派| 久久99久久99精品免观看吃奶 | 精品国色天香一卡2卡3卡| 好男人 好资源在线 视频| 国产在线无遮挡免费观看| 国产在线精品国自产拍影院同性| 国产一本一道久久香蕉| 和老师做H无码动漫| 精品久久久久久国产| 久久99国产精一区二区三区| 久久久国产精品一区二区18禁| 久久人妻XUNLEIGE无码| 麻花豆传媒剧国产MV在线上-| 美女自拍高潮流白浆| 女人双腿搬开让男人桶| 欧美丰满熟妇乱XXXXX视频| 欧美最猛黑人XXXX黑人猛交3p| 人妻无码一区二区视频| 人人添人人妻人人爽频| 色综合久久一区二区三区| 无码口爆内射颜射后入| 亚洲AV中文无码乱人伦在线r▽| 亚洲卡5卡6卡7卡2021入口| 野花香高清视频在线观看免费 | 18禁黄网站禁片免费观看APP| 91精品人妻欧美一区二区三区| CHINA浴室洗澡VOYEUR| 成人无码精品一区二区三区亚洲区| 丰满少妇邻居找我泻火| 国产刺激一区二区| 好深好大再浪一点| 老首长曰杨钰莹好爽| 欧美最猛性XXXXX大叫| 色婷婷亚洲婷婷七月中文字幕| 无码国产孕妇一区二区免费AV| 亚洲爆乳精品无码一区二区| 一本久久综合亚洲鲁鲁五月天| 777亚洲熟妇自拍无码区| 超碰97人人做人人爱可以下载| 国产精品国产三级欧美二区| 精品久久人妻AV中文字幕| 免费国产在线精品一区| 日韩成人无码专区一视频| 小SAO货撅起屁股扒开GIF动| 亚洲性啪啪无码AV天堂| TOUGHTESTED硬汉系列| 国产粉嫩馒头无套内在线观看免费| 国模少妇一区二区三区| 浪潮AV一区二区三区| 日本WV一本一道久久香蕉| 无人区码一码二码三码是什么意思| 亚洲欧美日韩国产精品一区 | 无码少妇一区二区性色AV| 亚洲精品无码AV中文字幕电影网| 中国熟妇内谢69XXXXX软件| 宝贝这里没人给我好吗| 国产精品自在拍一区二区不卡| 九九爱WWW免费人成视频| 农村人乱弄一区二区| 少妇搡BBBB搡| 亚洲欧美综合区丁香五月小说| 99久久国产综合精品五月天喷水| 国产SUV精品一区二区69| 久久99久国产精品66| 日本XXXXXXXXX69| 亚洲AV无码一区二区在线蜜桃| 中文JAPANESE在线播放| 公的大龟慢慢挺进我的体内| 久久WWW免费人成一看片| 人妻在厨房被侮辱高清版| 亚洲AV永久无码精品一区| av 成人 亚洲无码| 国产亚洲精久久久久久无码77777| 久久综合激的五月天的歌词| 色妞AV永久一区二区国产AV开| 亚洲欧洲无卡二区视頻| 不文女学堂在线观看| 精品无码AV一区二区三区不卡| 人妻丰满熟妇ΑⅤ无码区| 亚洲AV无码专区电影在线观看| 99精品电影一区二区免费看 | 日日日日做夜夜夜夜无码| 亚洲色无码中文字幕手机在线 | 极品无码国模国产在线观看| 翘臀后进少妇大白嫩屁股| 色欲国产麻豆一精品一AV一免费 | 无码专区国产精品第一页| 亚洲婷婷五月综合狠狠爱| 成人片黄网站色大片免费观看| 狠狠做五月深爱婷婷| 人人妻人人澡人人爽人人精品图片 | 小寡妇一夜要了六次| 18禁黄网站禁片免费观看APP| 国产精品久久久久久亚洲影视| 免费观看亚洲人成网站| 性生生活色欲片性按摩| А√天堂中文最新版在线种子| 精品人妻系列无码人妻不卡 | 亚洲VA在线VA天堂VA不卡| ZOZOTOWN| 久久久久免费看成人影片| 天堂资源官网在线资源| 92午夜少妇极品福利无码电影| 国内一区二区三区香蕉AⅤ| 人人人妻人人澡人人爽欧美一区| 亚洲日韩国产精品第一页一区| 番剧初恋不可能是亲姐姐| 免费无码又爽又刺激高潮软件| 亚洲AV激情无码专区在线下载 | 中文字幕人妻不在线无码视频| 国产女主播高潮在线播放| 人妻含泪让粗大挺进| 伊人色综合一区二区三区| 国产精品视频一区二区三区无码| 欧美成人精品三级又大又粗| 亚洲乱码日产精品BD在线看 | 国产亚洲综合欧美视频| 日韩欧美亚洲每日更新在线| 中年人妻丰满AV无码久久不卡 | 99久热RE在线精品99RE| 精品国产AⅤ无码一区二区蜜桃| 熟妇人妻午夜寂寞影院| chinese人妻无码人妻| 久热中文字幕无码视频| 亚洲AV永久无码天堂网| 国产成人精品一区二区视频| 欧美午夜一区二区福利视频| 伊人久久大香线蕉AV仙人| 好吊视频一区二区三区| 婷婷久久综合九色综合97| 草草浮力影院禁止18进入| 免费视频玩乳吃奶不遮挡网站 | 波多野结衣乳喷高潮视频| 蜜臀av无码少妇一区二区三区| 亚洲欧洲日产国码AⅤ| 韩国免费A级毛片| 无人区码一码二码三码区别图片| 大香伊蕉AⅤ在人线国产| 欧美熟妇SEXFREE| 中文字幕AV高清片| 极品少妇的粉嫩小泬看片| 香蕉AV福利精品导航| 国产成人亚洲精品无码AV大片| 日本熟妇色XXXXXBBB日本| 97丨九色丨国产人妻▌| 巨大垂乳日本熟妇挤奶| 亚洲熟妇无码八V在线播放| 黑人异族XXXⅩ吊大| 小雪被老外黑人撑破了视频| 国产成人精品一区二区三区免费 | 麻豆文化传媒精品观看网站| 亚洲人亚洲精品成人网站| 狠狠色噜噜狠狠狠777米奇| 羞羞漫画十八禁啪啪漫画免费 | 成人免费A级毛片无码片在线播放 成人免费A级毛片无码片2022 | 无码午夜福利片在线观看| 东北老熟女疯狂作爱视频| 日韩乱码人妻无码中文字幕视频 | 黑人刚破完处就三P| 亚欧免费无码AⅤ在线观看蜜桃| 国产精品天天看天天狠| 脱岳裙子从后面挺进去| 国产丰满大屁股XXXX| 偷炮少妇宾馆半推半就激情| 国产成人精品福利一区二区三区 | 一边做一边说国语对白| 久久久精品人妻无码专区不卡| 亚洲日韩精品A∨片无码加勒比| 久久99精品久久久久久不卡| 亚洲中文字幕久久精品无码VA| 久久久久无码专区亚洲AV| 永久免费无码国产| 免费夜色污私人影院在线观看|